― Project Scope Announcement & Periodic Project Updates
Del Norte Revitalization Project has begun in downtown Del Norte
Rio Grande County— The Town of Del Norte and Colorado Department of Transportation along with contracting partner, RMS Utilities, Inc. will begin a Main Street Revitalization project on July 8, immediately following the July 4th holiday weekend. Construction will include new curb and gutter, sidewalks, ADA compliant curb ramps, pedestrian street lights, crosswalks, pavement markings, signage, drainage improvements, water service lines and fire hydrants alongside US Highway 160 (Grand Avenue) in the Town of Del Norte from Alder Street east to Cherry Street. The project is expected to be completed by January of 2025.
Travel Impacts
- Working hours will be from 7:00 a.m. to 7:00 p.m. Monday through Friday. Crews will begin working on one block at a time.
- Motorists will encounter partial lane and shoulder closures throughout the project work zone and in the intersections.
- Vehicles, bikes and pedestrians should expect some travel impacts throughout the construction of this project. Pedestrians can expect sidewalk closures.
- Access to business will be maintained, but may be temporarily altered.
- Motorists are urged to watch for construction personnel and equipment in the work zone.
Project Benefits
The project is part of CDOT’s Revitalizing Main Streets grant program that enhances transportation safety and strengthens the connection of people to main streets and central economic hubs.
“We are pleased to be the recipient of this grant program,” said Mayor Shelly Burnett “The project in downtown Del Norte will encourage physical activity and enhance our local economy through several improvements to the town’s infrastructure.”
- New Americans with Disabilities Act (ADA) sidewalks, curb ramps and crosswalks will make pedestrian crossings accessible to people with disabilities, required by federal law
- Improvements along the corridor will provide safer access and mobility for residents and visitors
- New lighting allows better visibility for locals, businesses, and travelers
- Colored concrete to add esthetics for Del Norte’s business district
Project Contact Information
For additional information about this project, contact the project team.
- Project webpage: www.codot.gov/projects/
- Project hotline: 719-589-4263
- Project email: frontdesk@rmsutilities.com
Town of Del Norte Office: 719-657-2708
Latest Construction Updates from the Contractor
The sidewalks are closed for safety reasons, so please do not cross construction zone areas. And do not etch or engrave your ART WORK in the wet concrete, we do not want to have to redo the sidewalks. Thank you
Downtown Revitalization Project Update
Construction Progress Updates of June 12, 2025
Alder to Cedar
Asphalt is complete
Cedar to Pine
Asphalt and concrete complete
Pine to Colombia
Asphalt is set up for Friday 6/13
Handicap ramps will do this week
Colombia to Spruce
Asphalt will be done on Monday or Tuesday
Sidewalks finished
Concrete should be finished end of the week/beginning next week
Spruce to Oak Street
Sub grade is completed
Curb and gutter forming scheduled
Intersection at Spruce will be closed and demoed after pacing on Friday
Oak to Cherry Street
Demo to start next week
Safe Driving along Construction Work Zone
The sidewalks are closed for safety reasons, so please do not cross construction zone areas. And do not etch or engrave your ART WORK in the wet concrete, we do not want to have to redo the sidewalks. Thank you
Construction Progress Updates of May 21, 2025
Alder to Cedar
Asphalt is complete
Cedar to Pine
Asphalt and concrete complete
Pine to Colombia
Curb and gutters poured
Sidewalk is in progress
Conduit and light fixtures installed
Colombia to Spruce
Demo is complete
Conduit in progress
Schedule
Pine to Columbia
Asphalt scheduled
Addressing manhole on the intersection of Pine and Hwy 160
Columbia to Spruce
Concrete for Light poles will be poured
Prep and prepare grade for sidewalk
DUE TO THE MEMORIAL HOLIDAY WORK WILL CEASE AT NOON ON FRIDAY, MAY 23, 2025 AND WILL NOT START UP AGAIN UNTIL TUESDAY, MAY 27, 2025
Downtown Revitalization Project Update April 30, 2025
Downtown Revitalization Project Update
The sidewalks are closed for safety reasons, so please do not cross construction zone areas. And do not etch or engrave your ART WORK in the wet concrete, we do not want to have to redo the sidewalks. Thank you
Construction Progress Update as of April 30, 2025
Alder to Cedar
Paving today and tomorrow
Cedar to Pine
Poured curb yesterday
Forming sidewalk and preparing to pour concrete
Pine to Columbia
Demolition
Scheduled work
Alder to Cedar
Colored concrete next week
Light poles next week
Cedar to Pine
Pour sidewalk Thursday or Friday
Pine to Columbia
Next week will prep subgrade and install conduit and light poles
Downtown Revitalization Project Update March 1, 2025
Rio Grande County— Town of Del Norte and contract partner RMS Utilities, Inc. will begin a spring start up of the Grand Avenue Revitalization Project between the week of March 17, 2025 and March 31, 2025, depending on weather. Construction will start on the South- side of Grand Avenue at Alder Street east to Cherry Street.
The project began construction in July 2024 and started on the North-side of Grand Avenue and it included new curb and gutter, sidewalks, ADA compliant curb ramps, pedestrian street lights, crosswalks, pavement markings, signage, drainage improvements, water service lines and fire hydrants alongside US Highway 160 (Grand Avenue) in the Town of Del Norte from Alder Street east to Cherry Street.
Please remember the sidewalks are closed for a reason, your safety, so please do not cross construction zone areas. And do not etch or engrave your ART WORK in the wet concrete, we do not want to have to redo the sidewalks. Thank you
Downtown Revitalization Project Update 12/09/2024
Rio Grande County— Town of Del Norte and contract partner RMS Utilities, Inc. will begin a winter shutdown of the Grand Avenue Revitalization Project on Friday, December 13th. The project began construction in July and will include new curb and gutter, sidewalks, ADA compliant curb ramps, pedestrian street lights, crosswalks, pavement markings, signage, drainage improvements, water service lines and fire hydrants alongside US Highway 160 (Grand Avenue) in the Town of Del Norte from Alder Street east to Cherry Street.
Work Completed
During the 2024 construction season crews completed work on the north side of Grand Avenue. Curb and gutter, sidewalks, ADA compliant curb ramps, pedestrian street lights, crosswalks, pavement markings, signage, drainage improvements, water service lines and fire hydrants have been completed.
When work begins in the Spring of 2025, crews will start work on the south side of Grand Avenue.
Project Benefits
The project is part of CDOT’s Revitalizing Main Streets grant program that enhances transportation safety and strengthens the connection of people to main streets and central economic hubs.
“We are pleased to be the recipient of this grant program,” said Mayor Shelly Burnett “The project in downtown Del Norte will encourage physical activity and enhance our local economy through several improvements to the town’s infrastructure.”
- New Americans with Disabilities Act (ADA) sidewalks, curb ramps and crosswalks will make pedestrian crossings accessible to people with disabilities, required by federal law
- Improvements along the corridor will provide safer access and mobility for residents and visitors
- New lighting allows better visibility for locals, businesses, and travelers
- Colored concrete to add esthetics for Del Norte’s business district
Travel Impacts
During the winter shutdown, motorists will not encounter any construction-related traffic control or delays. When work resumes in the spring motorists should plan for partial lane and shoulder closures.
The project has an anticipated start date of April 2025.
Project Contact Information
For additional information about this project, contact the project team.
- Project hotline: 719-589-4263
- Project email: frontdesk@rmsutilities.com
Downtown Revitalization Project Update 10/28/2024
The sidewalks are closed for a reason, your safety, so please do not cross construction zone areas. And do not etch or engrave your ART WORK in the wet concrete, we do not want to have to redo the sidewalks. Thank you
Construction Progress Update
Cherry to Oak – Install Lights
Oak to Spruce –Install lights
Spruce to Columbia Avenue –Install lights
Columbia to Pine –Install lights
Pine to Cedar November 1- November 14
Pour concrete
Prep Asphalt
Install lights
Cedar to Alder November 1- November 26th
Demo
Install conduit
Light pole bases
Pour concrete
Prep Asphalt
Pave Asphalt
Install lights
Winter Shut-down week of November 25th
Downtown Revitalization Project Update 09/17/2024
The sidewalks are closed for a reason, your safety, so please do not cross construction zone areas. And do not etch or engrave your ART WORK in the wet concrete, we do not want to have to redo the sidewalks. Thank you
Construction Progress Update
Cherry to Oak
- Install Signage
- Install Lights
Oak to Spruce
- Pour colored concrete
- Prep Asphalt
- Pave Asphalt
- Install lights
Spruce to Columbia Avenue
- Pour curb and gutter
- Pour sidewalk
- Pour colored concrete
- Pave Asphalt
Columbia to Pine- Week of September 25th
- Demo existing sidewalks
- Water Service installation
- Electrical conduit
Downtown Revitalization Project Update 08/20/2024
Construction Progress Update
Cherry to Oak
- Pouring concrete
- Valley pan today
- Light pole bases are complete
iii. Handicap ramps today
- Removal of Asphalt along 160
Oak to Spruce
- Conduit has been placed
- Demo and excavation complete
iii. Prepping light pole bases
- Will pour concrete next week
2-week outlook
- Cherry to Oak complete
- Oak to Spruce concrete complete
iii. Demo and excavation of Spruce to Columbia Avenue